Mike Holt Enterprises Electrical News Source

NEC Questions and Answers based on 2017 NEC - February 2018

For EC&M Magazine

By Mike Holt, NEC® Consultant

Here's the follow-up to yesterday's newsletter.
This includes the answers to the questions sent, so you can see how you did.

ECM Q&A Image Figure 01

Note: The answers to these questions are based on the 2017 NEC.
Underlined text indicates a change in the rule for the 2017 NEC.

Q1. Does the NEC limit the number of service drops or service laterals allowed on a building?
A1. A building can only be served by one service drop or service lateral, except as permitted by (A) through (D) [230.2].

Author's Comment:
• A service is the conductors and equipment for delivering electric power from the electric utility to the premises served [Article 100]. Types of services provided from the utility include service drops and service laterals.

(A) Special Conditions. Additional services are permitted for the following:
(1) Fire pumps
(2) Emergency systems
(3) Legally required standby systems

Author's Comment:
• A separate service for emergency and legally required systems is permitted only when approved by the authority having jurisdiction [700.12(D) and 701.12(D)].

(4) Optional standby power
(5) Parallel power production systems
(6) Systems designed for connection to multiple sources of supply to enhance reliability

Author's Comment:
• To minimize the possibility of simultaneous interruption, the disconnecting means for the fire pump, emergency system, or standby power system must be located remotely away from the normal power disconnecting means [230.72(B)].

(B) Special Occupancies. By special permission, additional services are permitted for:
(1) Multiple-occupancy buildings where there's no available space for supply equipment accessible to all occupants, or
(2) A building or other structure so large that two or more supplies are necessary.

(C) Capacity Requirements. Additional services are permitted:
(1) If the capacity requirements exceed 2,000A, or
(2) If the load requirements of a single-phase installation exceed the electric utility's power capacity, or
(3) By special permission.

Author's Comment:
• Special permission is defined in Article 100 as the written consent of the authority having jurisdiction.

(D) Different Characteristics. Additional services are permitted for different voltages, frequencies, or phases, or for different uses, such as for different electricity rate schedules.

(E) Identification of Multiple Services. If a building is supplied by more than one service, or a combination of feeders and services, a permanent plaque or directory must be installed at each service and feeder disconnecting means location to denote all other services and feeders supplying that building, and the area served by each. Figure 01

Q2. When does the NEC consider service conductors as being installed outside of a building?

A2. Conductors are considered outside of a building when they're installed [230.6]:
(1) Under not less than 2 in. of concrete beneath a building. Š
(2) Within a building within a raceway encased in not less than 2 in. of concrete or brick.
(3) In a vault that meets the construction requirements of Article 450, Part III.
(4) In a raceway not less than 18 in. below a building.
(5) Within rigid or intermediate metal conduit that passes directly through an eave but not a wall of a building. Š

Q3. Does the Code allow branch circuit and feeder conductors to be installed in a service raceway containing service conductors?
A3. Feeder and branch-circuit conductors aren't permitted to be installed in a service raceway containing service conductors [230.7]. Š

Ex 1: Grounding electrode conductors or supply-side bonding jumpers are permitted in a service raceway with service conductors.

Ex 2: Conductors used for load management with overcurrent protection are permitted in service raceways with service conductors.

Warning: Overcurrent protection for the feeder or branch-circuit conductors can be bypassed or a fault can occur if service conductors are mixed with feeder or branch-circuit conductors in the same raceway and a fault occurs between the service and feeder or branch-circuit conductors.

Author's Comment:
• This rule doesn't prohibit the mixing of service, feeder, and branch-circuit conductors in the same service equipment enclosure.
• This requirement may be the root of the misconception that line and load conductors aren't permitted to be installed in the same raceway. It's true that service conductors aren't permitted to be installed in the same raceway with feeder or branch-circuit conductors, but line and load conductors for feeders and branch circuits can be in the same raceway or enclosure.

Post a Comment View Comments Subscribe Unsubscribe
Comments
  • We installed a 200-amp breaker panel in a suberb of Chicago. In the past they were on the 2011 nec code requirement where only the living areas needed arc falt breakers. Now they have changed to the 2014 code and want all the breakers in the panel to be arc falt breakers. (Including microwave and appliance kitchen outlets) We are having all kinds of problems with them tripping with saws and microwaves running and had to change to normal breakers. Is there something that I can show the city that there is not a use for arc falt breakers in some locations such as the sump pump, and kitchen circuits?

    Dennis Evenson  February 15 2018, 12:27 am EST

Reply to this comment
* Your Name:
   Your name will appear under your comments.

* Your Email:
   Your email address is not displayed.
* Comments:

Email Notification Options:
Notify me when a reply is posted to this comment
Notify me whenever a comment is posted to this newsletter