Selected Electrical Incidents and Occurrences - Fourth Quarter - October to December, 2007
 

 

Topic - Safety
Subject - Selected Electrical Incidents and Occurrences - Fourth Quarter - October to December, 2007

September 30, 2008
This newsletter was sent to 26223 newsletter subscribers

Ask a Question |  Weekly Code GraphicQuizzes |  Free Stuff InstructorsOnline Training Products | Seminars | SubscribeUnsubscribe
[ image1 Post Comments | View Comments | Notify Me When Comments Are Added ] Web Page Version [Printer-Friendly]    

Selected Electrical Incidents and Occurrences in Canada

Fourth Quarter – October to December, 2007

 

Date             Program      Location      Incident Description

 

Fatalities:

 

October 3rd            Construction         Toronto                 Electrical apprentice doing wiring for temporary lights, was

                                                                                                installing cable inside portable power centre when he made

                                                                                                contact with 600 volts.  600 volts was feeding a transformer

                                                                                                that supplied power for lights and 120 volt power tools.

 

 

Critical Injuries:

 

 

October 23rd          Industrial               Brampton               Worker doing vacuuming, knocked cover off 120 volt adapter.

                                                                                                Worker received a shock, sat down, then lay down before

                                                                                                losing consciousness.

 

November 10th       Construction         Toronto                 Worker was doing work in a junction box, made contact

                                                                                                with 120 volt wiring in box.  Worker lost consciousness

                                                                                                from contact.

 

November 20th       Construction         Mississauga         Worker received 2nd and 3rd degree burns from an electrical

                                                                                                contact, while working in an electrical box.  No details given

                                                                                                of work being done at the time, or of system voltage.

 

 

Non-Critical Injuries:

 

October 2nd            Construction         Carrick                    Conveyor on top of concrete truck hit overhead line while

                                                                Township              truck was backing up.  Truck driver shaken up, taken to

                                                                                                hospital for observation.

 

October 3rd            Construction         Etobicoke              Worker installing a driveway, discovered a buried pipe.  Tried

                                                                                                to cut pipe with hacksaw, pipe contained a 27.6 kV cable.

                                                                                                Worker received burns to hand and face.

 

October 4th             Mining                   Matachewan         Crew felt an electrical tingle while installing ground support

                                                                                                screening.  No details given on source of stray current.

 

October 6th             Industrial               Toronto                 Worker received a shock from touching a microwave oven

                                                                                                while also touching a metal fridge.  Worker taken to hospital

                                                                                                for observation, microwave taken out of service.

 

October 15th           Industrial               Toronto                 Licensed electrician tried to use pliers to continue to open the

                                                                                                partially open door of a 400 amp fused disconnect switch. 

                                                                                                Explosion happened, main breaker tripped to clear fault.

                                                                                                Worker taken to hospital, no details given of any injuries.

 

October 19th           Industrial               Tiverton                 Worker using a hand-held radiation meter, made contact with

                                                                                                bare wires next to handle.  Wires energized at 1500 volts,

                                                                                                worker taken to hospital.

 

October 27th           Industrial               Whitby                  Worker doing diagnostic testing on panel, received 350 volt

                                                                                                electrical shock.  Body reaction to shock caused a fracture to

                                                                                                left shoulder.

 

November 5th         Industrial               Ottawa                   Worker using screwdriver while working around battery in

                                                                                                car.  Screwdriver hit battery terminal, worker received burns

                                                                                                under his wristwatch.

 

November 6th         Construction         Kingston               Worker made electrical contact, taken to hospital.  No other

                                                                                                details of event given.

 

November 7th         Construction         Toronto                 Worker doing work in ceiling space, made contact with his

                                                                                                hand with 347 volt wiring.

 

November 8th         Industrial               Burlington             Worker doing commissioning testing of communications board

                                                                                                on power conditioning unit, received shock from 480 volts.

 

November 8th         Construction         Rockland               Worker received an electrical shock from 347 volts.

                                                                                                Scaffolding was in contact with energized cable.

 

November 11th       Mining                   Sudbury                 Worker received burns to arm from electrical contact.  Worker

                                                                                                was connecting 600 VDC flexible cable to slag car for

                                                                                                dumping.

 

November 20th       Industrial               Burlington             Worker was doing power washing, spray hit an electrical

                                                                                                panel.  Worker received a shock, taken to hospital for

                                                                                                observation.

 

November 20th       Construction         Toronto                 Picker truck being used to install winter protection panels,

                                                                                                truck contacted 150 kV overhead line.  Operator of truck

                                                                                                taken to hospital for observation.

 

November 22nd      Construction         Kapuskasing         Worker received minor electrical contact burns to his back

                                                                                                when he backed into an exposed wall plug.

 

November 24th       Construction         Cambridge             Workers using elevating work platform.  Extension cord

                                                                                                plugged into receptacle at base of unit, unit was moved, cord

                                                                                                stretched then broke.  Energized part of cord touched platform,

                                                                                                worker on platform was touching platform and metal outside

                                                                                                of the platform.  Worker received a shock.

 

November 26th       Industrial               Oshawa                  Electrical box blew up in front of worker, worker received

                                                                                                2nd degree burn to right wrist.  No details given of work being

                                                                                                done at the time, or of system voltage.

 

November 30th       Industrial               London                  Worker using vacuum cleaner, received a shock as she tried

                                                                                                to remove plug from wall receptacle.  Cord in poor condition.

 

 

December 13th       Construction         Niagara Falls         Contractor doing trenching, dug up a primary cable.  One

                                                                                                worker experienced a tingling sensation, sent to hospital.

 

December 14th       Construction         Nanticoke              Worker received a shock while plugging a 110 volt grinder

                                                                                                into an extension cord.  Worker taken to hospital for

                                                                                                observation.

 

December 20th       Industrial               St Marys                Building owner doing work on electrical panel, explosion

                                                                                                occurred.  Worker’s hands were black, hair was smoking.

                                                                                                Details of work being done at the time, and voltage of panel

                                                                                                were not given, but panel was rated for 600 amps.

 

December 24th       Industrial               Toronto                 Non-worker touched coverplate of wall-mounted switch,

                                                                                                received burns to four fingers of left hand.

 

 

Powerline Contacts – No Injuries:

 

October 1st             Construction         Hamilton                Contact made with overhead 13.8 kV line, equipment details

                                                                                                not given.

 

October 1st             Construction         Markham               Buried cable cut, no other details of event given.

 

October 1st             Construction         Thunder Bay         Truck struck overhead secondary lines, lines taken down.

 

October 2nd            Construction         Aylmer                   HiHoe dug up buried 220 volt cable.

 

October 3rd            Construction         London                  Crew stringing overhead lines, anchor holding pole broke.

                                                                                                lines hit another circuit energized at 4 kV.

 

October 4th             Construction         Toronto                 Backhoe hit buried 16 kV cable.  Cable had been located and

                                                                                                uncovered about 1 metre to west of contact point.  Backhoe

                                                                                                dug too deep.

 

October 4th             Construction         Scarborough         Excavator hit primary cable, not specified if cable was buried

                                                                                                or an overhead line.

 

October 5th             Construction         Smithville               Crew installing gas lines, hit 240 volt buried line.

 

October 5th             Construction         Oshawa                  Backhoe contacted buried cable, voltage of cable not given.

 

October 9th             Construction         Brampton               Excavator hit pole, causing it to fall.  Pole had 27.6 kV

                                                                                                circuit on it.

 

October 10th           Construction         Hamilton                Contact made with 240 volt buried cable, no other details of

                                                                                                event given.

 

October 11th           Industrial               Hamilton                Contact made with overhead 240 volt cable, no other details

                                                                                                of event given.

 

October 15th           Construction         Underwood           Boom truck contacted 8 kV overhead line.

 

 

October 15th           Construction         Thunder Bay         Utility workers made contact with power lines, no other details

                                                                                                of event given.

 

October 15th           Construction         Hamilton                Contact made with overhead 240 volt cable, no other details of

                                                                                                event given.

 

October 15th           Construction         Moorefield            Boom of excavator made contact with overhead line, voltage

                                                                                                of line not given.

 

October 17th           Construction         Guelph                   HIAB crane contacted 8 kV overhead line.

 

October 18th           Construction         Barrie                      Excavating equipment contacted buried 13 kV cable.

 

October 18th           Construction         Brampton               Contact made with 16 kV buried line, no details given of

                                                                                                equipment involved.

 

October 22nd          Construction         Saugeen Shores   Backhoe hit buried 240 volt cable.  Locates were wrong.

 

October 22nd          Construction         St. Catharines       Contact made with buried 120 volt cable, no other details

                                                                                                of event given.

 

October 24th           Construction         Toronto                 Workers working around exposed buried cables, one cable

                                                                                                started to spark then exploded.  No details given on work

                                                                                                being done around the cables at the time.

 

October 24th           Construction         Toronto                 Excavator cut a buried 600 volt cable,

 

October 25th           Construction         Burlington             Excavator cut a buried cable, voltage of cable not given.

 

October 25th           Construction         Toronto                 Supervisor climbing ladder to roof holding piece of pipe.

                                                                                                Pipe contacted high voltage overhead lines, no injuries

                                                                                                reported.

 

October 29th           Construction         Dundas                  Contact made with 240 volt overhead line, no other details

                                                                                                given.

 

October 29th           Construction         Woolwich              Dump truck traveling with raised box, tore down two spans of

                                                                Township              primary cable.

 

October 30th           Construction         Hamilton                Contact made with 240 volt buried cable, equipment in use not

                                                                                                specified.

 

October 30th           Construction         Sundridge              Dump truck raised its box, hit overhead lines, voltage of lines

                                                                                                not specified.

 

October 31st           Construction         Bradford                Worker drilling screws into hydro pole, contacted a cable,

                                                                                                voltage of cable not given.

 

November 1st         Construction         Vaughan                                Backhoe hit buried power line, voltage of line not given.            

 

November 1st         Industrial               Barrie                      Forklift being used to unload rebar, made contact with HV

                                                                                                overhead line.

 

November 5th         Construction         Hamilton                Contact made with 13 kV buried line, no other details given.

 

November 6th         Industrial               Kincardine             Tow truck pulling another vehicle out of a ditch, hit hydro

                                                                                                pole.  Knocked off power to entire town.

 

November 8th         Construction         Kanata                   Doing excavating, hit buried primary line.  No other details

                                                                                                given.

 

November 9th         Construction         Oakville                  Equipment boom hit 120 volt overhead line, lines caused pole

                                                                                                to snap.  Pole also held a 27 kV circuit.

 

November 9th         Industrial               Welland                 Worker was using a screwdriver to install a wire in a meter

                                                                                                base.  Screwdriver slipped, contacted 120 volt conductor.

 

November 13th       Construction         Waterloo               Cut through floor, hit 208 volt cable.

 

November 13th       Construction         Hamilton                Contact made with buried 240 volt cable.  Details of

                                                                                                equipment involved not given.

 

November 14th       Construction         St. Catharines       Event classified as power line contact, event description

                                                                                                mentioned 120 volt street lighting.  No other details given.

 

November 14th       Construction         Cambridge             Excavator made contact with 4800 volt overhead line.

 

November 14th       Construction         Barrie                      Worker doing drilling, hit primary cable.

 

November 14th       Industrial               Hamilton                Contractor made contact with 240 volt overhead line, no other

                                                                                                details of event given.

 

November 14th       Construction         Ottawa                   Worker using a SAWSALL to cut hole in plywood wall, cut

                                                                                                into 600 volt cable.

 

November 19th       Construction         Brampton               Excavating equipment dug up a buried 27 kV line.

 

November 19th       Construction         Coldwater              Dump truck with raised box hit telephone cable, caused pole

                                                                                                to snap.

 

November 20th       Industrial               Sault Ste. Marie    Clearing trees, tree fell on powerlines.  Voltage of lines not

                                                                                                given.

 

November 21st       Construction         Thunder Bay         Contractor clearing trees for 7200 volt line, tree limb

                                                                                                contacted overhead conductor.

 

November 23rd      Construction         Toronto                 Doing digging to get soil sample, hit electrical conduit.

 

November 23rd      Construction         Hamilton                Contact made with overhead 240 volt line, no other details

                                                                                                of event given.

 

November 23rd      Construction         Toronto                 Excavator severed a buried line, voltage of line not given.

 

November 26th       Construction         Estaire                    Ground wire of overhead line hit and broken.  No details given

                                                                                                of equipment that made the contact.

 

November 27th       Construction         Richmond Hill       Worker doing shovel digging, contacted secondary line at base

                                                                                                of pole.

 

November 28th       Construction         Hamilton                Contact made with buried 110 volt cable.  No other details of

                                                                                                event given.

 

December 3rd         Construction         Hamilton                Contact made with overhead 120 volt line, no other details of

                                                                                                event given.

 

December 5th         Construction         Hamilton                Contact made with overhead 110 volt line, no other details of

                                                                                                event given.

 

December 5th         Construction         Toronto                 Core drill cut into buried 13.8 kV primary line.

 

December 6th         Construction         Hamilton                Crane contacted 4 kV overhead line.

 

December 6th         Construction         Tiverton                 Cutting old drywall with hacksaw, contacted cable.  Voltage

                                                                                                of cable not given.

 

December 6th         Construction         Burlington             Worker using concrete pumping boom, contacted 24 kV line.

 

December 7th         Construction         Toronto                 Contractor hit 600 VDC trolley line, brought down about

                                                                                                200 feet of line.

 

December 8th         Construction         Cambridge             Worker turned off 110 volt breaker at panel, went to cable and

                                                                                                cut into cable with side cutters.  Wrong cable.   Arcing

                                                                                                damage to side cutters, no injuries.

 

December 12th       Construction         Barrie                      Contact made with primary cable, no other details given.

 

December 12th       Construction         Port Hope              Dump truck contacted fibre-optic line

 

December 12th       Construction         Orillia                      Boom truck contacted 13.8 kV overhead line.

 

December 16th       Construction         Oakville                  Scaffolding hit power line

 

December 18th       Construction         St Williams            Excavator boom contacted 240 volt overhead line.

 

December 26th       Industrial               Cambridge             Contractor cut through energized lighting cable.

 

December 31st        Industrial               Welland                 Worker drove into hydro pole, snapped it in half.

                                                                                                Line was energized at 27.6 kV.

 

 

Electrical Equipment – No Injuries:

 

October 23rd          Construction         Waterloo               Worker removing fluorescent light fixture, power was ON.

                                                                                                Pliers made contact with outside of fixture, power went OFF.

                                                                                                No injuries reported from event.

 

November 9th         Industrial               Toronto                 Explosion happened as workers were removing a circuit

                                                                                                breaker from the rack.  Voltage of breaker was not given.

                                                                                                No injuries reported from event.

 

December 20th       Mining                   Sudbury                 Workers washing down the floor of a working area beside a

                                                                                                conveyor.  Receptacle was located on wall just below the floor

                                                                                                area.  Light was plugged into receptacle, fire started from

                                                                                                water getting into receptacle.  Fire went out when light was

                                                                                                unplugged.

DATA SUMMARY – Fourth Quarter:

 

                                Fatals:                   Criticals:              Non-criticals:                      Powerline             Electrical

                                                                                                                                                Contacts:              Equipment:

 

2007                            1                                3                                23                                        69                              3

2006                            2                                1                                24                                        69                              0

 

2005                            1                                2                                26                                        44                              2

2004                            0                                6                                19                                        28                              0

2003                            0                                7                                19                                        37                              0

2002                            0                                4                                15                                        37                              1

2001                            5                                9                                28                                        33                              1

 

2000                            2                                8                                15                                        30                              1

1999                            2                                7                                21                                        30                              1

1998                            1                                8                                15                                        29                              2

 

 

 

 

And Finally…..

 

December 21st        Industrial               Cambridge             School teacher was acting as a reindeer in a school

                                                                                                Christmas play.  Hopping around, hyper-extended her left

                                                                                                ankle.  Taken to hospital.

 

 

Information taken from Ontario Ministry of Labour MIS database

Report prepared: May 30, 2008

 

Assembled by:     Michael Reiser, P.Eng.,

                                Engineer, PSS – Kitchener District

                                E-Mail:   mike.reiser@ontario.ca

 

 

 

Click here to post a comment
[ View More Newsletters ] [ Send to a Friend ] [ Post Comments | View Comments | Notify Me When Comments Are Added ]

Copyright © Mike Holt Enterprises, Inc. All rights reserved.
This article is protected by United States copyright and other intellectual property laws and may not be
displayed or published on the internet without the prior written permission of Mike Holt Enterprises, Inc.

http://www.MikeHolt.com     1-888-NEC-CODE (1-888-632-2633)

Experiencing a Problem? Click Here

 
Comments
  • It's regrettable that we don't get similar info/reports from the other States/Provinces of North America. Otherwise, a very useful item (to which I look forward seeing when it comes out) with a wealth of useful info. Tnx for bringing it to us.

    Jim Green
    Reply to this comment


Add Your Comments to this Newsletter
* Your Name:
   Your name will appear under your comments.

* Your Email:
   Your email address is not displayed.
* Comments:

This newsletter is closed to new comments.

Email Notification Options:
Notify me when a reply is posted to this comment
Notify me whenever a comment is posted to this newsletter